Synchronizing all changes

In the Pending Changes view, you can synchronize all changes by performing both a rebase and a deliver operation.

Procedure

To synchronize all changes:
  1. Open the Pending Changes view. In the VersionVault Navigator, select the VersionVault view in which you want accept incoming changes. Right-click the view and select Show Pending Changes from the context menu in the VersionVault Navigator or click the Show Pending Changes icon show pending changes icon on the VersionVault toolbar.
  2. In the Pending Changes view, click on the Synchronize All Changes icon sychronize all changes icon on the Pending Changes view toolbar.
  3. Open the Pending Changes view. In the VersionVault Navigator, select the VersionVault view in which you want accept incoming changes. Right-click the view and select Show Pending Changes from the context menu in the VersionVault Navigator or click the Show Pending Changes icon show pending changes icon on the VersionVault toolbar.
  4. In the Pending Changes view, click on the Accept All Incoming Changes icon accept all incoming changes icon on the Pending Changes view toolbar.
  5. If you have not already configured a default rebase operation for the current view, the Default Rebase Configuration dialog box displays. Specify whether to rebase to the recommended baseline or the latest baseline and click OK.
  6. The Ready to Complete Rebase dialog box appears. Specify whether to leave the rebase operation in its current state, complete the rebase operation, or cancel the rebase operation. and click OK. If you chose to complete the rebase operation, click OK in the Rebase confirmation dialog box.
  7. If you have not already configured a default deliver operation for the current view, the Default Deliver Configuration dialog box displays. Ensure that the target stream and the integration view are correct and click OK.
    Note that you can also specify these options in the HCL VersionVault Explorer > Integration > Rebase and Deliver preferences.
  8. The Ready to Complete Deliver dialog box appears. Specify whether to leave the deliver operation in its current state, complete the deliver operation, or cancel the deliver operation. and click OK.
  9. If you chose to complete the deliver operation, click OK in the Deliver confirmation dialog box.
    The Pending Changes view now shows no outgoing changes.
  10. To enable others to access the changes you have delivered, make a new baseline by navigating to the integration stream, right-clicking the stream name, and selecting Make Baseline, specify the options you want and clicking OK.