Accepting incoming changes

In the Pending Changes view, you can accept incoming changes by performing a rebase operation.

Procedure

To accept incoming changes:
  1. Open the Pending Changes view. In the VersionVault Navigator, select the VersionVault view in which you want accept incoming changes. Right-click the view and select Show Pending Changes from the context menu in the VersionVault Navigator or click the Show Pending Changes icon show pending changes icon on the VersionVault toolbar.
  2. In the Pending Changes view, click on the Accept All Incoming Changes icon accept all incoming changes icon on the Pending Changes view toolbar.
  3. If this is the first time that you have selected this option for the current view, the Default Rebase Configuration dialog box displays. Specify whether to rebase to the recommended baseline or the latest baseline and click OK.
    Note that you can also specify this option in the HCL VersionVault Explorer > Integration > Rebase and Deliver preferences, under the When rebasing options.
  4. The Ready to Complete Rebase dialog box appears. Specify whether to leave the rebase operation in its current state, complete the rebase operation, or cancel the rebase operation, and click OK.
  5. If you chose to complete the rebase operation, click OK in the Rebase confirmation dialog box.
    The Pending Changes view now shows no incoming changes.