Scheduling ProcessFutureOrders job

The ProcessFutureOrders command processes future orders. For locked orders in states 'C', 'M', 'I', 'B', 'L', 'A', and have some order items whose inventory status in 'FUT', this scheduler command allocates inventory for these order items, re-prepares orders, then process the orders.

Procedure

  1. Open the Administration Console, and select Site on the Administration Console Site/Store Selection page.
  2. Click Configuration > Scheduler . A list of jobs that are scheduled to run is displayed.
  3. Click New. The Schedule Job window opens.
  4. From the Job command list, select ProcessFutureOrders.
  5. Complete the following fields:
    OptionDescription
    Start time Enter 00:00
    Interval Enter 3600
    Priority Enter 8
  6. Click OK. Your job is listed on the Scheduler Status Display page and will run at the specified start time.