Changing availability for a virtual destination
About this task
If you need to manually change the status of a virtual
destination, follow these steps:
- Enter the S row command from the MODIFYING A WORK STATION IN THE
CURRENT PLAN panel. The following panel is displayed:
Figure 1. EQQMWDES - Modifying a virtual workstation destination status in the CP EQQMWDES --- MODIFYING A VIRTUAL WORKSTATION DESTINATION IN TH Row 1 to 2 of 2 Command ===> Scroll ===> CSR Enter the row command S to select a destination for modification, or I to browse system information for the destination. Row Dest. Status Extended Status cmd Name '''' ******** A '''' VDEST2 O ******************************* Bottom of data ********************************
- Enter the S row command. The following panel is displayed:
Figure 2. EQQMWSRV - Modifying a virtual workstation destination status in the CP EQQMWSRV --- MODIFYING A VIRTUAL WORKSTATION DESTINATION IN THE CP ------------ Command ===> Enter/change data below: Enter the O command above to modify open time intervals Enter the V command above to vary work station status Work station : VWS1 Destination : VDEST2 Status : Offline Waiting for connection CONTROL ON SERVERS ===> Y Control on parallel servers, Y or N CONTROL ON K1 ===> Y Control on critical resource K1 , Y or N CONTROL ON K2 ===> Y Control on critical resource K2 , Y or N
- Enter the V command. The following panel is displayed:
Figure 3. EQQMWS2P - Modifying workstation status in the current plan EQQMWS2P ----- MODIFYING WORK STATION STATUS IN THE CURRENT PLAN -------------- Command ===> Enter data below, and issue END command to change the status: Work station : VWS1 Destination : VDEST2 Current Status : Offline NEW STATUS ===> _ A active, F failed O offline Fail/offline options : STARTED OPERATIONS ===> _ R restart, L leave, E set to error
The values you enter on this panel affect the workload. If you change the destination status to F or O, specify also an action for the operations that are already started on the workstation, by using the STARTED OPERATIONS field.
A status change on a virtual destination might cause a change in the global status of the virtual workstation it refers to.
Use this panel to make the virtual destination unavailable. You can set the global status to:- Offline
- All the destinations are offline, meaning that communication is lost between the controller and the tracker on the system that the destination represents.
- Failed
- All the destinations are in failed status, meaning that the operating system detected a failure on the system that the destination represents.
- Active
- At least one destination is active.
- Inactive
- Some destinations are offline and others are in failed status.
Note: When you enter the END command on this panel, the status change is effective immediately, even if you enter the CANCEL command on the EQQMWSRV panel.To modify open time intervals and adjust the destination fixed resources and parallel servers, enter the O command on the EQQMWSRV panel. The following panel is displayed:Figure 4. EQQMWS1L - Modifying open intervals of a virtual WS destination EQQMWS1L MODIFYING OPEN INTERVALS OF A VIRTUAL WS DESTINATION Row 1 to 3 of 3 Command ===> Scroll ===> CSR Change data in the rows, and/or enter any of the following row commands: I(nn) - Insert, R(nn),RR(nn) - Repeat, D(nn),DD - Delete Virtual work station : VWS1 Virtual destination : VDEST2 Control on servers : Yes Control on K1 : Yes Control on K2 : Yes Row From To Modified cmd YY/MM/DD HH.MM YY/MM/DD HH.MM ps K1 K2 '''' 07/06/07 00.00 07/06/07 05.59 65000 99 99 '''' 07/06/07 06.00 07/06/07 17.59 65000 99 99 '''' 07/06/07 18.00 07/06/07 23.59 65000 99 99 ******************************* Bottom of data ********************************
To indicate that no operation can run on the selected destination, set the number of parallel servers to 0.
If you alter the interval details, the altered interval is never replaced by daily planning extend and re-plan functions. For example, consider the following sequence of events:- You modify the number of parallel servers between 18.00 and 23.59 on 07/06/07 to 25.
- You change the database to close VDEST2 at 20.00 on 07/06/07.
- You extend the plan at 15.00.