Fields displayed in ready and error lists

This appendix contains a list of fields that you can display in the ready list and the error handling list. In this table, the Length column is the maximum length (in bytes) of the data in the field.

Table 1. Fields available for display in ready and error lists
Column title Length Description of column contents
PR# 04 Number of predecessor operations
PS# 03 Number of parallel servers required by the operation
UPR# 04 Number of uncompleted predecessor operations
R1# 03 Number of 1st WS resources required by the operation
R2# 03 Number of 2nd WS resources required by the operation
SR# 03 Special resources referenced by the operation
SU# 04 Number of successor operations
Arrived 08 Operation arrival date, actual if arrived
Ard 03 Operation arrival day, actual if arrived
time 05 Operation arrival time, actual if arrived
Application 16 Application ID
Act dur 07 Actual duration of the operation
A 01 Automatic error-completion indicator, Y or N
Ended 08 End date of the operation, or blank
End 03 End day of the operation, or blank
time 05 End time of the operation, or blank
H 01 Automatic hold/release indicator, Y or N
Owner 16 Application owner ID
Started 08 Actual start date of the operation
Std 03 Actual start day of the operation
time 05 Actual start time of the operation
S 01 Automatic job submission, Y or N
Application text 24 Verbal description of the application
JLOG 01 Status of job log retrieval
CLN_Ty 01 Cleanup type
CLN_Re 01 Cleanup result
RC_St 01 Internal restart and cleanup status, for debugging only
C 01 Critical path, F-1st (Y=on path, N=not)
S 01 Current status of the operation
T 01 Dependency type, P=predecessor, S=successor
W 01 Deadline WTO, Y or N
E dur 05 Estimated duration of the operation
Errc 04 Error code of the operation, otherwise blank
Destination 08 Execution destination ID
Form no. 08 Form number or blank
Authgrp 08 Authority group
Ia date 08 Application input arrival date (after MCP)
Ia day 03 Application IA day, (<) preceding month, (>) next
Ia time 05 Application input arrival time (after MCP)
I start 08 Intermediate start date after interrupt
ISt 03 Intermediate start day after interrupt
time 05 Intermediate start time after interrupt
Jobname 08 Job name
C 01 Job, SYSOUT class, or blank
Job id 08 JES job ID
S 01 Job status (I) init, (H) held, (Q) released
L 01 Latest out time passed
Last out 08 Latest out date of the operation
Lo 03 Latest out day of the operation
time 05 Latest out time of the operation
Last upd 08 Time stamp of last MCP update in the format MMDDHHmm (month, day, hour and minutes)
H 01 Operation manually HELD by user
N 01 Operation NOPed by user
no. 03 Operation number
Deadline 08 Deadline date of the operation
Dl 03 Deadline day of the operation
time 05 Deadline time of the operation
Plan ia 08 Planned input arrival date of operation
Ia 03 Planned input arrival day of operation
Oi 01 Operator instructions available
time 05 Planned input arrival time of operation
Plan end 08 Planned end date of the operation
End 03 Planned end day of the operation
time 05 Planned end time of the operation
P 01 On preparation workstation, Y or N
P 01 Priority of the operation
Pl start 08 Planned start date of the operation
St. 03 Planned start day of the operation
time 05 Planned start time of the operation
Transp 06 Transport time, from previous WS to this WS
Rdr date 08 Date the reader recognized the job card
Rdr t 05 Time the reader recognized the job card
L 01 Time job suppressed if late, Y or N
R 01 Reroutable operation, Y or N
R 01 Restartable operation, Y or N
RSNC 01 Reason code
St 02 Operation status, current and extended status
T 01 Time job indicator, Y or N
Operation text 24 Verbal description of the operation
User data 16 Operation user data
U 01 Urgency indicator
RE 01 Operation rerouted, Y or N
ws 04 Workstation
T 01 Workstation type
WTO ws 01 Workstation is a WTO
Dur. 07 Actual duration, if completed, otherwise estimated
Inp arr 08 Operation IA date, actual if arrived
Ia 03 Operation IA day, actual if arrived, otherwise planned
time 05 Operation IA time, actual if arrived
X 01 Extended status of the operation
Ended 08 End date, actual if ended, otherwise planned
End 3 End day, actual if ended, otherwise planned
time 05 End time, actual if ended, otherwise planned
Start 08 Operation start date, actual if started
St 03 Operation start day, actual if started
time 05 Operation start time, actual if started
Actual dur 10 Actual duration of the operation in seconds
Est dur 08 Estimated duration of the operation in seconds
Duration 10 Actual duration, if completed, otherwise estimated in seconds