Performing deliver and rebase operations

You can deliver either activities or baselines. If you deliver from the integration stream, you must deliver baselines. The target of your deliveries can be to your parent stream or to an alternate target stream.

If you work in an HCL VersionVault MultiSite environment, deliver operations may differ. If your site does not master a target stream, you cannot complete deliver operations to that stream. UCM provides a variation of the deliver operation called a remote delivery. In the remote delivery, you post your work if your target stream is not mastered by the local PVOB. If you work as a project integrator at a site of a target stream that is mastered by the local PVOB, you need to find work that has been posted for delivery at another site and complete the deliver operation at your site.

You typically rebase your stream to baselines in your parent stream.