Starting plans

You start a plan by changing the status. Select the status transition Start Plan. After you start a plan, all participants can work on the plan.

About this task

To start a plan, complete the following steps.

Procedure

  1. Go to the Summary tab of the plan you want to start.

    Click Operations > Plans. Click Actions(Folder image) and select a view (such as My Plans or All Plans) that includes plans with "Not Started" as the status.

  2. Click Change Status and select Start Plan or Start Plan with comments from the menu.
  3. Optional: If you chose Start Plan with comments, type your comments and click Continue.

Results

The plan status changes to Green circleIn Progress.