Step 4. Add a dependency on the shadow job

After defining the shadow job you can add the cross dependency.

Add a cross dependency on a job instance scheduled in a remote engine plan, by defining a normal dependency on the shadow job that:
  • Points to the remote job on which you want to create the cross dependency.
  • Is defined on a local remote engine workstation that points to the engine where the remote job is defined.

Because the remote job instance status transition is mapped into the shadow job status transition, the status of the cross dependency is represented by the status of the normal dependency.