Recovery process

About this task

Follow the steps listed below to recover your HCL Workload Automation for Z environment to start-of-day processing.
  1. Allocate all required data sets. The JCL required should be based on the sample library (SEQQSAMP) members EQQPCS01 and EQQPCS02.
  2. Restore data from the last backup taken before the start-of-day required. For example, if recovery to start-of-day for Tuesday is required, then backups from Monday should be used for the recovery.
  3. Specify JOBSUBMIT (NO) and CURRPLAN (NEW) on the JTOPTS statement and then start the controller address space. Start additional address spaces required for tracker subsystems.
  4. If required, use the mass update function in the Application Description dialog to make out-of-effect business systems that you do not need to process in the secondary center.
  5. Submit a long-term plan MODIFY ALL batch job.
  6. Submit a daily plan TRIAL for the required planning period, and check the results. It is recommended that you start the planning period from 00:00 on the date required to reduce the number of undecided occurrences included in the current plan.
  7. Submit a daily plan EXTEND batch job for the required planning period. Use 00:00 as the start time. When the new current plan is created, use the HCL Workload Automation for Z dialogs to check that occurrences and resources are in the correct status before starting job submission.
  8. Change CURRPLAN(NEW) to CURRPLAN(CURRENT) on the JTOPTS statement.