When the approval process is in progress for an approval task, the approval task is
locked. If a project manager clicks a locked approval task, an error appears. You might need to
add another step after the approval process starts. To avoid this error, you add a task and then
change number the system assigns to the task.
Procedure
-
Decide what dependency option you want the new task or stage to use. Click In
series and select No dependencies, In
series, or In parallel.
Your selection remains in effect until you change it again.
- Select any row that is not locked.
Select
the row immediately below the locked approval task.
-
To add approvals or tasks, click Add row and then select
Task, Approval, Form
task, or Flowchart approval. To add stages, click
Add stage.
- Change the number that the system assigns to the new task
or stage so that it follows the locked task.
Suppose
that the locked task is 2.5 Review copy - informal (2.3).
Click the name of the new task and change its number to 2.6.
When you click in another spreadsheet cell, the system moves the new
task so that it is after task 2.5.