Using a baseline schedule

Before you begin

Before you create your projectsLists, On-demand Campaigns, or Corporate Campaigns, have the system administrator set up permissions and reminders as follows.

  • Set permissions so that only projectList, On-demand Campaign, or Corporate Campaign owners can update Target dates.
  • Set reminders (alerts) based on the Actual/ForecastActual dates.

About this task

While you work with a baseline schedule, team members perform the following high-level steps.

Procedure

  1. The owner sets the Target Start and End dates for each task.

    These dates stay fixed throughout the entire projectList, On-demand Campaign, or Corporate Campaign.

  2. As the projectList, On-demand Campaign, or Corporate Campaign progresses, team members update the Actual/ForecastActual dates with real data.