To run the Overdue Milestone report
About this task
The Overdue Milestone report shows all overdue milestones with task end dates that fall between the selected start and end dates. You can filter the report by using the Report Start Date and Report End Date parameters as well as the Task Status and Project Status parameters.
Procedure
Results
The report displays a list of milestones, grouped by the milestone owner, sorted by project code, and containing the following columns: Milestone Owner, Project Code, Milestone, Task Number, Status, Task Name, End Date, Forecast/Actual End, Days Late, and Notes®.