EQQEX01 - EQQEX08

EQQEX01I

THE EXTERNAL ROUTER TASK HAS STARTED

The external router task has successfully completed initialization. The external router task handles the interface to the operation-initiation exit, EQQUX009, which is used to start operations at user-defined destinations.

The external router task processing continues.

None.

EQQEX02I

THE EXTERNAL ROUTER TASK HAS ENDED

The external router task has ended either because the controller is in the process of shutting down or as a result of an operator modify command to terminate this task or a related task.

HCL Workload Automation for Z processing continues.

None.

EQQEX03E

THE EXTERNAL ROUTER TASK HAS ENDED DUE TO PROCESSING ERRORS

The external router task has terminated due to processing errors.

Normal HCL Workload Automation for Z processing continues.

If the cause of the error is due to a problem in the operation-initiation exit, EQQUX009, correct the error and restart the controller. If the cause of the error cannot be determined, take a dump of the HCL Workload Automation for Z address space, retain a copy of the message log and the job tracking data sets and contact IBM Software Support.

Contact your system programmer.

Check the HCL Workload Automation for Z message log and the dump data sets for additional information that describes the problem.

EQQEX04W

NO ROUTING FOR USER DESTINATIONS IS IN EFFECT

The external router task has not been able to load the operation-initiation exit, EQQUX009.

Normal HCL Workload Automation for Z processing continues. Operations at user-defined workstations are not started.

Determine why HCL Workload Automation for Z was unable to find or load the operation-initiation exit, EQQUX009. When the problem has been corrected restart the controller.

If the controller includes workstations with user-defined destinations, contact your system programmer.

EQQEX05E

THE EXTERNAL ROUTER HAS TERMINATED DUE TO AN INITIALIZATION FAILURE

The external router task could not acquire the resources required for normal operation.

External router processing is terminated.

Correct all errors and restart HCL Workload Automation for Z.

Contact your system programmer.

Review previous messages in the HCL Workload Automation for Z message log.

EQQEX06E

A SEVERE ERROR IN THE EXTERNAL ROUTER TASK HAS CAUSED ONE OR MORE REQUESTS TO BE LOST

The external router task encountered an error processing elements on the EXAQ. As a result, at least one queue element has been lost.

z/OS recovery/termination is requested to generate a dump. The external router task attempts to continue normal processing.

Save the message log, diagnostic and dump data sets, and contact IBM Software Support.

Review the HCL Workload Automation for Z message log data set, the EQQDUMP diagnostic data set, and the dump data set to determine the cause of the problem.

EQQEX07E

THE EXTERNAL ROUTER TASK ABENDED WHILE PROCESSING THE FOLLOWING REQUEST REQUEST

An abend prevented the external router task from processing a queue element.

z/OS recovery?termination is requested to generate a dump. The external router task attempts to continue normal processing.

Save the message log, diagnostic and dump data sets, and contact IBM Software Support.

Contact your system programmer.

Review the HCL Workload Automation for Z message log data set, the EQQDUMP diagnostic data set, and the dump data set to determine the cause of the problem.

EQQEX08E

THE EXTERNAL ROUTER TASK HAS IGNORED THE FOLLOWING QUEUE ELEMENT: REQUEST

The external router task has detected an invalid queue element on its queue.

The element is discarded from the external router queue. The task continues normal processing.

Save the message log (EQQMLOG) and the current plan (EQQCPxDS) and contact IBM Software Support.

Contact your system programmer.

Review the HCL Workload Automation for Z message log data set.