To use a test stream to stabilize code, perform the steps shown in the following
figure.
Figure 1: A test stream
to stabilize a baseline
Procedure
Make a baseline that contains the changes to be tested. (For more information, see
PA.BL1 in the figure).
Do one of the following:
Create a development stream dedicated to stabilization. (For more information, see stream
DS in the figure).
Rebase a dedicated development stream to the baseline that
you made.
Use as the foundation baseline of the test stream the baseline that you created. (For more
information, see PA.BL1 in the
figure).
Control the changes that are being made in the stabilization
stream DS.
Other work from development streams
in the project can be delivered to the integration stream without
affecting the stabilization stream. Fixes implemented in the stabilization
stream are isolated from activities delivered to the integration stream.
When the code in the test stream is stable, make a baseline in the test stream. (For more
information, see PA.BL1.S in the
figure).
Deliver the baseline PA.BL1.S to the integration
stream.
In the integration stream, recommend the baseline from
the stabilization stream so that development streams can rebase to
it.