Upgrading Sametime 11.5 and Sametime 11.6 Kubernetes deployments
Before you begin
To upgrade from Sametime 11.5 or Sametime 11.6 to Sametime 12, the following conditions must be satisfied:
- HCL Sametime Meetings 11.5 or Sametime 11.6 must be installed and configured.
- Sametime has access to a MongoDB server. You can re-use your existing
MongoDB server.Note: There are no special configuration steps required for the database. It automatically creates when the Sametime server connects to MongoDB.
- Prepare migration steps before upgrading to the latest Sametime version. The
upgrade gives you a new community and proxy component that replaces your
existing components.
- Have a back-out plan. Create a backup of the following files.
- docker-compose.yml
- custom.env
- .env
- Have a back-out plan. Create a backup of the following files.
- Docker Compose 1.29 or higher must be installed in your Sametime environment.
About this task
To upgrade from Sametime 11.5 or Sametime 11.6 to Sametime 12, follow these steps:
Procedure
- Extract the 11.5, 11.6, or 11.6 IF1 zip files to any directory on either the master Kubernetes host itself or on a machine which has management access to the Kubernetes cluster.
-
Deploy the docker images.
./load.sh
- Edit values.yaml where needed.
-
Run the command below to detect the current settings and copy or update them as
needed.
./prepareDeployment.sh
- Answer Y to proceed. If N (no) is answered, the install script prompts for the necessary steps.
-
Run the command below to upgrade to Sametime 12.
helm upgrade meetings -n default helm/.
Revert to the previous version
About this task
If you encounter a problem, run the helm command to roll back to the previous version.